What to do about the existing cases?There remained the question about what to do about the cases that had been scheduled for surgery. In taking the action they had, the anaesthetists had forced the delay or transfer of potentially all open-heart pediatric cardiac surgical cases that would normally have been done at the Children's Hospital. Once the review had been agreed to, Bishop and others broached the question of performing some operations while the review was being undertaken. Giddins and Odim (among others) supported the view that low-risk open-heart operations could still be performed during the review. McNeill testified that originally the anaesthetists had wanted a moratorium on all open-heart cases, including low-risk cases. Following the creation of the Wiseman Committee, she testified that "we left with having agreed that we would not withdraw entirely, and you know, that we would set up a review process to address things that were going on in the program." (Evidence, page 13,262) Since a review of the program had been set in place, the anaesthetists felt that it was impossible for them to refuse to participate in all open-heart operations. However, they maintained their concern about the degree of complexity of the cases that were being considered or undertaken. At the meeting, McNeill and Ullyot agreed that the anaesthetists would participate in less-complex, low-risk open-heart cases but that they would not participate in cases of higher risk until the review was complete.
|
Current | Home - Table of Contents - Chapter 7 - What to do about the existing cases? |
Next | Informing HSC senior management |
Previous | The decision to conduct a review |
Section 1 | Chapter 1 - Introduction to the Issues |
Chapter 2 - Pediatric Cardiac Issues | |
Chapter 3 - The Diagnosis of Pediatric Heart Defects and their Surgical Treatment | |
Chapter 4 - The Health Sciences Centre | |
Section 2 | Chapter 5 - Pediatric Cardiac Surgery in Winnipeg 1950-1993 |
Chapter 6 - The Restart of Pediatric Cardiac Surgery in 1994 January 1, 1994 to May 17, 1994 |
|
Chapter 7 - The Slowdown; May 17 to September 1994 | |
Chapter 8 - Events Leading to the Suspension of the Program September 7, 1994 to December 23, 1994 |
|
Chapter 9 - 1995 - The Aftermath of the Shutdown January to March, 1995 |
|
Section 3 | Chapter 10 - Findings and Recommendations |
Appendix 1 - Glossary of terms used in this report | |
Appendix 2 - Parties to the Proceedings and counsel | |
Appendix 3 - List of witnesses and dates of testimony | |
Diagrams | |
Tables | |